G2 LNG is a Louisiana based energy development company. G2 is comprised of leaders with deep roots in the Bayou State, as well as decades of business, industry, and governmental experience.


G2 LNG is committed to delivering a stable supply of low cost natural gas globally while respecting the environment and community of which we are a part.


PROJECT DEVELOPMENT

G2’s initial development efforts will be a 14 mtpa LNG export facility in Cameron Parish, Louisiana.  Investors are committed to fund activities associated with the Federal Energy Regulatory Commission permitting process leading to final approval to construct.

G2 is currently in advanced discussions with long-term customers in Asia, Europe, India and the Caribbean and have signed LOI’s reflecting the progress of these discussions. G2 will be participating in all phases of the LNG value chain.

G2 filed an FTA/non-FTA license application with the U.S. Department of Energy in March, 2015 and on July 17, 2015 was granted a license to transport LNG to FTA countries. G2 expects commencement of delivery by early 2021.

Project Timeline Estimate

  • June, 2014                                                                

    G2 LNG is formed

  • December, 2014                                                          

    Option completed on 500 acres in Louisiana

  • March, 2015                                                 

    Application filed with DOE for FTA/non-FTA LNG export license

  • March, 2015                                                 

    Option completed on 266 contiguous acres in Cameron Parish

  • July, 2015                                                                                  

    DOE approval of G2 FTA Export license 

  • December, 2015                                                          

    Start of NEPA pre-filing process

  • 2nd Quarter, 2016                                                          

    Formal FERC Application

  • 2nd Quarter, 2017                                                          

    Final Off-take Agreements

  • 2nd Quarter, 2017                                                          

    FERC final order to construct expected

  • 3rd Quarter, 2017                                                          

    Department of Energy Non-FTA Export license

  • 3rd Quarter, 2017                                                          

    Project financing plan agreement

  • 1st Quarter, 2021                                                          

    Commencement of delivery


LNG Export project will provide a LNG solution that is price competitive in the global energy market.